AQL 2.5 vs AQL 1.0: Sample Sizes, Accept Numbers and What the Report Must Show

The ISO 2859-1 level II maths behind the sample size, the accept/reject numbers that actually decide the verdict, why tightening from 2.5 to 1.0 costs almost nothing, and the fields a usable inspection report carries.

By VeraBOM & B2B Partner engineering & export team9 min read
AQL 2.5 vs AQL 1.0: Sample Sizes, Accept Numbers and What the Report Must Show — illustration

AQL is a lot verdict, not a quality level

An AQL number answers one question: given this lot, how many defective samples will you tolerate before the whole lot is rejected? It says nothing about the average quality of what arrives. A supplier who writes "AQL 2.5 inspected" is describing a sampling procedure, not a defect rate.

ISO 2859-1 and its ANSI/ASQ Z1.4 twin define the plans. AQL 2.5 means a lot whose true defect level is 2.5% will be accepted with high probability; AQL 1.0 gives that same acceptance probability at a 1% defect level. The tighter number does not guarantee fewer defects — it makes the same defect rate far more likely to fail the lot while the goods are still on the factory floor.

That is the whole commercial point. Inspection exists to move the sort-and-rework conversation to the place where labour is cheap and the container is still open, instead of your own warehouse six weeks later.

The sample size comes from lot size and inspection level

General inspection level II is the ISO 2859-1 default and the one to assume unless the order says otherwise. For the same lot, level I draws roughly half the sample of level II and level III roughly 1.5-2× more. Level II is where producer risk and inspection cost balance; level III is for a supplier with a bad history, or where a single missed defect is expensive.

Lot size maps to a code letter, and the code letter maps to a sample size n at level II: 151-280 pcs → G → n = 32; 281-500 → H → 50; 501-1,200 → J → 80; 1,201-3,200 → K → 125; 3,201-10,000 → L → 200; 10,001-35,000 → M → 315; 35,001-150,000 → N → 500; 150,001-500,000 → P → 800.

Special levels S-1 to S-4 exist for destructive or costly testing — S-4 on a 1,201-3,200 lot gives code letter G and n = 32, against 125 at level II. They are legitimate when the test destroys the part. Using S-3 to save an afternoon on a cosmetic check is not sampling, it is hoping.

Accept and reject numbers are what decide the outcome

Single sampling, normal inspection, code H (n = 50): AQL 4.0 → Ac 5 / Re 6; AQL 2.5 → Ac 3 / Re 4; AQL 1.5 → Ac 2 / Re 3; AQL 1.0 → Ac 1 / Re 2; AQL 0.65 → the table gives an arrow, so you move down to n = 80 with Ac 1 / Re 2.

Code J (n = 80): AQL 2.5 → Ac 5 / Re 6; AQL 1.0 → Ac 2 / Re 3. Code K (n = 125): AQL 4.0 → Ac 10 / Re 11; AQL 2.5 → Ac 7 / Re 8; AQL 1.0 → Ac 3 / Re 4; AQL 0.65 → Ac 2 / Re 3. Code L (n = 200): AQL 2.5 → Ac 10 / Re 11; AQL 1.0 → Ac 5 / Re 6. Code M (n = 315): AQL 2.5 → Ac 14 / Re 15; AQL 1.0 → Ac 7 / Re 8; AQL 0.65 → Ac 5 / Re 6.

Worked example: a 3,000-piece lot is code K at level II, so 125 pieces are inspected either way. Under AQL 2.5 the lot passes with up to seven defectives and fails on the eighth. Under AQL 1.0 it fails on the fourth. If your assembly line jams at a 1% fallout, the 2.5 plan will keep passing lots you cannot use.

Classify defects before you choose a number

One AQL across all defects is the most common specification error. Split into critical (can injure a user or break a regulatory requirement: missing protective earth, cracked load-bearing weld, sharp burr on a handle), major (kills function or saleability: bore out of tolerance, spring rate off curve, leaking seal) and minor (cosmetic only: light tool mark, print offset).

A workable default is critical 0 / major 2.5 / minor 4.0. For safety-relevant work — lifting components, pressure parts, anything installed where people stand under it — use critical 0 / major 1.0 / minor 2.5. Critical at AQL 0 means zero acceptance: one critical defect in the sample rejects the lot, and most agreements additionally require a full screen of the lot.

Attribute plans count pass/fail and throw the measurement away. Where a characteristic is measurable and critical, ISO 3951-1 variables sampling extracts more information from the same n, and a Cpk ≥ 1.33 record from the factory gauges beats both. For springs the equivalent control is a load-at-length table with measured values at two or three defined lengths, not a nominal rate band.

When AQL 1.0 earns its keep — and when it does not

Demand 1.0 for the first three lots from a new factory, for any lot produced after a corrective action, and for parts where a defect stops a line: interface dimensions on CNC-machined parts, thread class and proof load on fasteners, sealing faces on valves. Also for anything sold under your own brand into a market with real product liability.

Here is the fact most buyers miss: tightening the AQL does not enlarge the sample. Sample size follows lot size and inspection level; the AQL only sets the accept number. Going from 2.5 to 1.0 on a 3,000-piece lot still means 125 pieces inspected — the acceptance threshold moves from seven to three. The lever that costs money is the inspection level, not the AQL.

So use the cheap lever freely. Where a 1.0 plan rejects too often, the answer is not a retreat to 2.5; it is tightened inspection under the switching rules, a supplier-side 100% sort with a recorded yield, or a process change. Loosening the accept number repeatedly teaches the factory what you will tolerate.

What a usable inspection report must show

Header: standard and edition cited (ISO 2859-1:1999 or ANSI/ASQ Z1.4), inspection level, sample size code letter, lot size presented, quantity actually inspected, date, location and inspector name. If the lot presented is smaller than the order quantity, that has to be visible on page one — inspecting an incomplete order and calling it a pass is the standard report trick.

Body: the Ac/Re used per defect class, the count found per defect with dated photos and sample IDs, and measured values against nominal ± tolerance showing the instrument used and its calibration date. A grid of "OK" ticks is a signature, not evidence. Ask for actual readings on every critical characteristic, from at least 10-32 pieces depending on the sample plan.

Tail: packing and marking verification (carton count, gross and net weight per carton, carton dimensions, shipping marks), the functional tests run and their results, the disposition (accept / reject / hold for sort) and the inspector signature. Where material traceability matters, the report should photograph the heat number on the sampled part and tie it to the EN 10204 3.1 certificate in the document pack.

Switching rules and the fail protocol

ISO 2859-1 switching is mechanical: tightened inspection begins when two of five consecutive lots are rejected and reverts to normal after five consecutive accepted lots. Reduced inspection becomes eligible only after ten consecutive accepted lots with stable production and approval by the responsible authority — it is never automatic. Quote the switching rule in the purchase contract so a rejection has a defined next step instead of a phone call.

Write the fail protocol before the inspection. Who pays for the sort, how many days the factory has to finish it, who re-inspects and at whose cost, what happens to the shipping date, and when the balance is released. A clause that works across a time zone: sort at the factory at supplier cost, re-inspect to the same plan under tightened mode, balance held until the passing report is issued.

Also define the second failure. Most agreements call for a third-party inspection at supplier cost, a 100% screen with a documented yield, or lot rejection with the goods held for credit. Leaving that blank is what converts a quality problem into a payment dispute.

Questions this guide raises

Which AQL should we specify for industrial components?

Critical 0, major 2.5, minor 4.0 is the workable default for machining, springs and fabrication. Move major to 1.0 for pressure, lifting and safety parts, for interface dimensions that stop an assembly line, and for the first three lots from any new factory.

Does AQL 1.0 mean a bigger sample than AQL 2.5?

No. Sample size is set by lot size and inspection level. On a 1,201-3,200 piece lot at level II both plans inspect 125 pieces; the acceptance number simply drops from 7 to 3 at AQL 1.0. Inspection time barely changes, which is why tightening is cheap.

Can we inspect 100% instead of sampling?

You can, and for small lots or safety-critical characteristics it is often right. But 100% screening is not 100% effective — visual screening typically catches 80-95% of the defects present — so keep a sampling audit on top of it, and note that destructive tests can never be run at 100%.