MOQ, Lead Time and Sample Policy: How a Real China Purchase Order Flows

What actually drives a 10-piece versus a 500-piece minimum, where the two weeks go, and how to structure a sample so it shortens the production phase instead of delaying it.

By VeraBOM & B2B Partner engineering & export team7 min read
MOQ, Lead Time and Sample Policy: How a Real China Purchase Order Flows — illustration

Why MOQ exists

Minimum order quantities are set by setup, not by greed. A forging die, an extrusion tool, an injection mould, a powder-coating line changeover or a cable extrusion colour change each cost the factory a fixed block of hours. Where MOQ looks high, it is usually because one of those operations is being triggered for you alone.

Two levers reduce it: choose sizes and materials already in the works schedule, or accept a small-lot surcharge that is openly stated on the quotation instead of buried in unit price.

Where the lead time goes

A typical custom metal part breaks down roughly as: material procurement 3-8 days, rough machining 4-8 days, heat treatment or plating 4-10 days (external processor queues are the usual surprise), finish machining 3-7 days, inspection and documentation 2-4 days, packing and inland transport 3-5 days. Add the port and shipping window separately.

That is why a 25-35 day promise is realistic and a 12-day promise on a plated, heat-treated part is usually optimism.

Structure the sample so it counts

Ask for the sample to be produced with the production route and the production fixture, not on a prototype machine. Request a dimensional report with actual values, photographs of the inspection, and the material certificate. Sign and date the report: that becomes the reference your future batches are judged against.

Deposit, balance and the moment of risk

The commercial risk in an export order moves when the deposit is paid. Market practice runs from 30% to 50% down, with the balance either against an approved inspection report before shipment or — with smaller export houses that would rather carry the payment risk themselves — in full before the container is loaded. Judge the trigger, not the percentage: money should move after you have seen measurements, and it should land in a corporate account with the same legal name as the invoice.

Inspection is a step, not an event

Agree the plan at order confirmation: what is checked, at what quantity, to which standard, and what happens on a fail. AQL 2.5 normal inspection with a written fail protocol protects both sides better than an after-dinner "we will check it".

Questions this guide raises

Can we order below MOQ to test the market?

Usually yes, with a small-lot surcharge. For most industrial parts we will quote a trial quantity so you can validate fitment and sell-in before committing to the tooling-driven quantity.

Who pays for samples and courier?

Standard stocked items are normally free with freight collect. Custom samples are charged and typically credited against the first production order.

What if the batch is late?

The purchase contract carries the agreed ship date and a remedy. Ask for weekly production photos, because visibility is worth more than a penalty clause nobody wants to invoke.

Written first reply within 1 working day; priced answer within 2-5 working days.